HQC Sets New Industry Record with Modular Construction
打印 2025-06-13 09:10 字体: [大] [中] [小]

Recently, the first dilution steam framework module for the 1.2 Million TPA Phase II Ethylene Plant in Tarim, jointly contracted by HQC Beijing Company and HQC Sixth Construction Company, has arrived at its installation location. The fabrication of the module weighing 436 tons in total was completed within 56 days, setting a record in the industry.

2025-06-13 来源: 责任编辑: